Status: Approved
Timeframe: 2017-2019
Area: State of Gujarat, Republic of India
AIIB Investment Amount: US$ 329 million
Total Project Cost: US$ 658 million
Co-financier: Government of Gujarat: US$ 329 million
E&S Category: B
Project Details: Construction and upgrading of all-weather rural roads to increase transportation access throughout the state of Gujarat in India.
Resettlement: None
CSO reports and organizations monitoring: Gender Action (2019): Unmet Gender Promises in AIIB’s Gujarat Project; PWESCR (2019): Gender Case Study from Gujarat
AIIB interactions to date: None
Further information: AIIB Page; Gender Action Scorecard
Last update: 31.12.2023
Kontakt

Dr. Nora Sausmikat
China desk/Campaigns on Multilateral Development Banks
nora.sausmikat [at] urgewald.org
+49 030 86329 22 32

Dr. Dustin Schäfer
Team Lead Campaigns Multilateral Financial Institutions
dustin [at] urgewald.org